Page 1 of 1
Confirmation screen
Posted: Sun Jul 01, 2012 2:17 pm
by Yves
I have a daily backup set to 2am. I would like to have confirmation that the backup went through correctly. I use to have a text screen confimation, but some how I don't anymore. I've searched but can't seem to find that option anymore
Can anyone help me find it?
Completion message
Posted: Mon Jul 02, 2012 3:12 pm
by Barry
The option to give a completion message is under Advanced Schedule Options. This option just adds a command line parameters to the backup job so you may prefer to use Microsoft Task scheduler to update the parameters manually:
The options are M for completion message or F if the message is to be displayed only if the backup fails.
Example:
If the backup job is called My Backup and there are no other parameters the command line parameter will look like this:
"My Backup|M"
Please note the quotes, this is because there is a space in the backup job name. The | character separates the job name from the parameters.
Barry
Posted: Sun Nov 18, 2012 1:24 am
by nikkil
Hi Yves, were you able to resolve this yet?